Consumer unit and meter cupboard

Upgrading your connection: how it works, what it costs and how long it takes

Two jobs that follow each other, two bills and six to twelve weeks of waiting. With the alternatives that are often cheaper.

Kevin HermansUpdated 19 August 20268 min read

Short answer

Upgrading is two jobs that follow each other: the grid operator adapts the connection, I adapt the installation. You apply yourself via mijnaansluiting.nl. Allow six to twelve weeks lead time and € 500 to € 1.500 in grid operator costs, plus € 2.231 for a complete new three-phase consumer unit.

What upgrading actually means

There are two things people call "upgrading" and they often get mixed up:

  1. Upgrading the connection. From 1x35A to 1x40A, or from single-phase to 3x25A. This is about the cable from the street and the main fuses. This is the grid operator's work, not an electrician's.
  2. Extending the consumer unit. More circuits, a bigger consumer unit. This is my work and can often be done without the grid operator.

Do you only want more circuits but are you still well within your connection capacity? Then you do not need to upgrade and it is simply a consumer unit job. See consumer unit replacement or, if it is purely about space, extending the meter cupboard.

When you really need to upgrade

Work it out before you apply. With 1x35A you have roughly 8 kW. Add up what can run at the same time:

Appliance Power
Induction hob (full) 7.400 W
EV charger single-phase 3.700 W
Heat pump 1.500 to 4.000 W
Washing machine 2.100 W
Tumble dryer 2.500 W
Dishwasher 2.000 W
Rest of the household 1.000 W

If what is realistically on at the same time comes to more than 8 kW, upgrading makes sense. But look at the alternatives first, because they are often cheaper. The circuit planner works this out room by room for you.

Alternatives that are often better

  • Load balancing on the EV charger. The car charges more slowly when the rest of the house needs a lot. Costs € 120 to € 220 and solves most of it. See EV charger at home: single-phase or three-phase.
  • Rewiring the induction hob to less power. Many hobs can be set to a lower total power. You can still cook perfectly well on it.
  • Spreading usage over time. The tumble dryer at night, the car between 23:00 and 07:00.
  • Only extending the consumer unit without changing the connection.

I say this explicitly because upgrading means more work and more turnover for me. If it is not needed, I say so.

Comparison card of upgrading versus alternatives with costs

Is it possible in your street?

Before you do anything else, do the grid congestion check on your postcode. In more and more neighbourhoods the grid is full and the grid operator no longer grants upgrades, or only in a year's time. You want to know that before you order the kitchen, not after.

How the application works

  1. Apply via mijnaansluiting.nl. You do this yourself, as the owner of the property. I can advise on what to apply for, but the application is in your name.
  2. The grid operator assesses it. They check whether the grid in your street can handle the capacity requested. In some neighbourhoods that is currently the bottleneck, not your own connection.
  3. Quote from the grid operator. It states what it costs and when they can do it.
  4. Accept and schedule. This is where the waiting time is.
  5. The grid operator comes. New cable or new main fuses, a new meter if it goes from single-phase to three-phase.
  6. I adapt the installation. New or modified consumer unit, dividing the circuits over the phases, testing, handover.

Steps 5 and 6 need to follow on from each other. In practice I plan my day straight after, or on the same day as, the grid operator, so you are not left with half an installation for days.

Lead time

Realistically six to twelve weeks from the application. In areas with grid congestion it can take longer, sometimes a lot longer. That is not something I have any influence over.

Important if you are renovating: apply early. If the kitchen is already ordered and the induction hob is lying on site, a ten-week wait is a problem. Apply as soon as the plan is ready.

What it costs

Two separate bills.

Grid operator (prices as of August 2026, indication)

Change Indication
1x35A to 1x40A € 200 to € 500
Single-phase to 3x25A, existing cable sufficient € 500 to € 900
Single-phase to 3x25A, new cable needed € 900 to € 2.000
Digging on your own property often at your own expense

These amounts differ per grid operator and per situation. The grid operator's quote is what counts, not my indication. There is more detail on three-phase connection costs.

Electrician (my side)

Item Indication excl. VAT
New three-phase consumer unit, 12 circuits, complete € 2.231
Converting an existing consumer unit to three-phase (if possible) € 700 to € 1.100
Redistributing the circuits over the phases and testing included
Call-out charge € 59,99 excl. VAT, same fixed rate nationwide

So allow € 2.700 to € 4.200 in total for a complete upgrade to three-phase. That is a serious amount and exactly the reason you should work out the alternatives first. How my hourly rate is made up is on what does an electrician cost.

Cost overview for upgrading, grid operator and electrician shown separately

The forgotten cost: the standing charge

A three-phase connection has a higher standing charge from the grid operator than a single-phase connection. You pay that every year, even if you do not use the capacity. Take that into account: over fifteen years it adds up.

What changes in the consumer unit

In a three-phase consumer unit the circuits are divided over three phases. Dividing them well means spreading the heavy users so that each phase carries roughly the same load.

This is where rushed work goes wrong. If the washing machine, tumble dryer and dishwasher all end up on L1 and the rest on L2 and L3, L1 trips while the other two do nothing. Then you have upgraded and you still have problems.

Ask for the measured load per phase at handover. A good electrician has measured it and can show you.

From my own work

At a house in Elsloo another firm had upgraded the connection to 3x25A. Two months later the customer called: still problems. When I measured, L1 was at 22 amps and L2 and L3 at 4 and 3 amps respectively. All the heavy circuits were on one phase. An afternoon of redistributing solved it. The upgrade itself had been fine, only the work after it was half done.

When to call an electrician

Before you apply. I am happy to work out with you whether an upgrade is really needed. That conversation costs you nothing and regularly saves an application that was not necessary.

Send a photo of your meter, of your main fuses and a short list of what you are planning via WhatsApp. Or request a quote straight away.

Call 043 204 18 26WhatsApp a photo

Frequently asked questions

Who applies for the upgrade?

You as the owner, via mijnaansluiting.nl. I can advise on what to apply for, but the application is in your name.

How long does an upgrade take?

Allow six to twelve weeks from the application. In areas with grid congestion it can take longer.

How long will I be without power?

The grid operator usually takes half a day, I take a day for the consumer unit. If the two follow on from each other, you are without power for one day.

Is an upgrade always possible?

Not always. In some neighbourhoods the grid is currently the limit. Check that in advance with the grid congestion check.

Will my energy bill go up?

The standing charge from the grid operator will. Your consumption does not change because of the upgrade itself.

Can I upgrade without a new consumer unit?

Sometimes, if the existing consumer unit is suitable for three-phase and there is space. Often it is more practical and not much more expensive to renew the consumer unit at the same time.

Further reading

Questions and comments

Ask your question below. Ask before 17:00 on a working day and you get an answer from Kevin himself the same day. No account needed, and your email address does not appear on the site.

This tells me you are not a computer program. Type the answer as a number, for example 12.

Ask your question

Only to let you know there is an answer. It does not appear on the site and does not go on a mailing list.

Comments are read before they appear on the site. I publish questions, corrections, experiences and criticism. I do not publish advertising, or advice that encourages people to work on a live installation.